Penerapan Earned Value Analysis (Analisis Nilai Hasil) terhadap Waktu untuk Memperkirakan Waktu Akhir Proyek Studi Kasus Proyek Pembangunan Gedung Layanan Bersama Fakultas Teknologi Pertanian Universitas Brawijaya Tahap I

Yahya, Moch Mustadz Rofani (2023) Penerapan Earned Value Analysis (Analisis Nilai Hasil) terhadap Waktu untuk Memperkirakan Waktu Akhir Proyek Studi Kasus Proyek Pembangunan Gedung Layanan Bersama Fakultas Teknologi Pertanian Universitas Brawijaya Tahap I. Undergraduate thesis, Fakultas Teknik Universitas Merdeka Malang.

[thumbnail of HALAMAN AWAL.pdf] Text
HALAMAN AWAL.pdf

Download (1MB)
[thumbnail of BAB I.pdf] Text
BAB I.pdf

Download (65kB)
[thumbnail of BAB II.pdf] Text
BAB II.pdf
Restricted to Repository staff only

Download (245kB)
[thumbnail of BAB III.pdf] Text
BAB III.pdf
Restricted to Repository staff only

Download (125kB)
[thumbnail of BAB IV.pdf] Text
BAB IV.pdf
Restricted to Repository staff only

Download (435kB)
[thumbnail of BAB V.pdf] Text
BAB V.pdf
Restricted to Repository staff only

Download (58kB)
[thumbnail of Daftar Pustaka.pdf] Text
Daftar Pustaka.pdf

Download (58kB)
[thumbnail of PLAGIASI.pdf] Text
PLAGIASI.pdf

Download (356kB)

Abstract

is hoped that effective time management will help complete the project within the allotted time, this is in accordance with the scope of the Researcher's work which is not in the Civil field but from Mechanical Electrical so that later it can be applied in Researcher work. The purpose of using result value analysis is to be able to estimate the extent to which the project to be implemented is in accordance with the work plan. The purpose of this research is to find out whether the implementation of the Earned Value Analysis (EVA) in estimating the final project completion time for 16 weeks of implementation is in accordance with the initial schedule and how the benefits of the Earned Value Analysis (EVA) concept are for project analysis. The method used in this research is descriptive quantitative.
This study estimates that the final project completion time is not in accordance with the initial project schedule plan. Since week 1 there have been delays in project implementation. The estimated time for project completion based on the 11th week is 146 days, while the planned time is 110 days, this indicates a delay of 36 days from what was planned. The application of Earned Value Analysis can be applied to overcome work delays, while the maximum delay that can be tolerated is 10% if the work progress is below 70%, but if the work progress is above 70% then the tolerable delay is 5%. If the delay tolerance is not met, it is certain that the work will be completed late and not according to schedule.

Item Type: Thesis (Undergraduate)
Additional Information: Moch Mustadz Rofani Yahya NIM : 17041000034
Uncontrolled Keywords: Control, time, result value, project
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction
Divisions: Fakultas Teknik > S1 Teknik Sipil
Depositing User: Gendhis Dwi Aprilia
Date Deposited: 04 Mar 2025 06:12
Last Modified: 04 Mar 2025 06:12
URI: https://eprints.unmer.ac.id/id/eprint/4438

Actions (login required)

View Item View Item