Analisis Faktor - Faktor Penyebab Keterlambatan pada Pelaksanaan Proyek Rekonstruksi Jembatan Sendangbumen

Jeharum, Fidelis Paskalis Yansen (2022) Analisis Faktor - Faktor Penyebab Keterlambatan pada Pelaksanaan Proyek Rekonstruksi Jembatan Sendangbumen. Undergraduate thesis, Fakultas Teknik Universitas Merdeka Malang.

[thumbnail of COVER.pdf]
Preview
Text
COVER.pdf

Download (5MB) | Preview
[thumbnail of BAB I.pdf]
Preview
Text
BAB I.pdf

Download (159kB) | Preview
[thumbnail of BAB II.pdf] Text
BAB II.pdf
Restricted to Repository staff only

Download (388kB)
[thumbnail of BAB III.pdf] Text
BAB III.pdf
Restricted to Repository staff only

Download (201kB)
[thumbnail of BAB IV.pdf] Text
BAB IV.pdf
Restricted to Repository staff only

Download (946kB)
[thumbnail of BAB V.pdf] Text
BAB V.pdf
Restricted to Repository staff only

Download (101kB)
[thumbnail of DAFTAR PUSTAKA.pdf]
Preview
Text
DAFTAR PUSTAKA.pdf

Download (40kB) | Preview
[thumbnail of HASILC EK PLAGIASI.pdf]
Preview
Text
HASILC EK PLAGIASI.pdf

Download (696kB) | Preview

Abstract

The Sendangbumen Bridge Reconstruction Project is included in the critical delaycriteria based on The Minister of Public Works Regulation No.43/PRT/M/2007. In theplanning the project will be completed in a hundred days of its work, but in theimplementation of the project exceeds such targets. In this study, the authors will findthe main factors causing the delay in the project, as well as the value of the percentageof how much influence the factor has on the delay in the project. This study uses anon-parametric statistical analysis method, in which there are two correlation theoriesin it, namely kendall correlation and spearman rank correlation. These two correlationswill result in the value of the correlation coefficient and the significance between thevariables causing project delay and project delay. The result of this study is that thereare three main factors causing delays in the sendangbumen bridge reconstructionproject, namely: strikes of handyman and worker workers due to payment problemsetc., there are frequent changes of artisans and workers, in the middle of project work,implementation in the field is not in accordance with the SOP (Standard OperationWork) which refers to existing regulations. There is a percentage value of kendall'stau_b of the three main factors causing delays, namely the factor Of strikes ofhandymen and workers due to payment problems etc. has a percentage of 18.06%,factors Often occur changes of handymen and workers, in the middle of project workhas a percentage of 30.91% and factors Implementation in the field does not matchSOP (Standard Operation Work) has a percentage of 20.53%.

Item Type: Thesis (Undergraduate)
Additional Information: Fidelis Paskalis Yansen Jeharum NIM : 18041000039
Uncontrolled Keywords: Project Delay, Factors Causing Delay
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TG Bridge engineering
Divisions: Fakultas Teknik > S1 Teknik Sipil
Depositing User: Gendhis Dwi Aprilia
Date Deposited: 16 Feb 2025 05:17
Last Modified: 16 Feb 2025 05:17
URI: https://eprints.unmer.ac.id/id/eprint/4327

Actions (login required)

View Item View Item