Perbandingan Waktu Dan Biaya Pada Metode Pelaksanaan Top-Down Dan Bottom-Up Proyek Apartemen X Kota Malang

Ramadhan, Muhammad Mahesa ORCID: https://orcid.org/0000-0001-5248-0884 and Kurniasari, Marisa Wahyu (2023) Perbandingan Waktu Dan Biaya Pada Metode Pelaksanaan Top-Down Dan Bottom-Up Proyek Apartemen X Kota Malang. Jurnal Spektran, 11 (2). pp. 127-133. ISSN 2302-2590 (Printed) ; 2809-7718 (Online)

[thumbnail of 99726-445-377790-1-10-20230829 (5).pdf]
Preview
Text
99726-445-377790-1-10-20230829 (5).pdf

Download (744kB) | Preview
[thumbnail of Plagiasi Jurnal Spektran Universitas Udayana Perbandingan Metode Top Down dan Bottom Up.pdf]
Preview
Text
Plagiasi Jurnal Spektran Universitas Udayana Perbandingan Metode Top Down dan Bottom Up.pdf

Download (1MB) | Preview

Abstract

Technological advances that occur every year make developments in the field of construction produce innovations in work implementation methods, one of which is the top-down method of implementation. This method allows the construction of the basement to be carried out simultaneously with the superstructure work which results in a fast project completion time. The purpose of this research is to compare the bottom-up implementation method that is usually used in projects with the top-down implementation method in terms of cost and implementation time. The research method used in this study is the quantitative method, for calculating implementation costs using the Work Unit Price Analysis (AHSP) method and for planning implementation time using the Microsoft Project 2016 application. The results obtained in this study are for implementation time analyzed using the Microsoft application Project 2016 resulted in the bottom-up method having a duration of 821 calendar days and the top-down method having a duration of 693 calendar days. For implementation costs using the bottom-up method, Rp. 534,974,570,850 and for the top-down method spent Rp. 538,861,461,837

Item Type: Article
Additional Information: Muhammad Mahesa Ramadhan NIDN: 0701029702
Uncontrolled Keywords: cost, bottom-up, top-down, time
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction
Divisions: Fakultas Teknik > S1 Teknik Sipil
Depositing User: Rita Juliani
Date Deposited: 27 Mar 2024 04:37
Last Modified: 27 Mar 2024 04:39
URI: https://eprints.unmer.ac.id/id/eprint/4152

Actions (login required)

View Item View Item