Keterlambatan Sekuensial dengan Analisis Kurva-S pada Proyek Pembangunan Terminal Seruni Point Bromo Tengger Semeru

Downloads

Downloads per month over past year

Santoso, Cornelia Agda (2024) Keterlambatan Sekuensial dengan Analisis Kurva-S pada Proyek Pembangunan Terminal Seruni Point Bromo Tengger Semeru. Masters thesis, Program Pascasarjana Universitas Merdeka Malang.

[thumbnail of HALAMAN AWAL.pdf]
Preview
Text
HALAMAN AWAL.pdf

Download (708kB) | Preview
[thumbnail of BAB V.pdf]
Preview
Text
BAB V.pdf

Download (279kB) | Preview
[thumbnail of DAFTAR PUSTAKA.pdf]
Preview
Text
DAFTAR PUSTAKA.pdf

Download (237kB) | Preview

Abstract

The construction of the Seruni Point Terminal project in the Bromo Tengger Semeru National Park area has been delayed. This is due to technical and non-technical factors. The technical factors that cause delays are labour factors, material factors and equipment factors. Non-technical factors that support the delay are weather factors and policy makers. The delay that occurred in the analysis of the results of the project report and the S-Curve. The method used is to comparethe S-curve of planning and execution. From the results of the analysis carried out, delays are divided into two types, namely sequential delays and sequential delays themselves. The two types of delays result from the comparison of the area underthe implementation curve. A comparison that results in 1.x means that it is delayed, while 0.x means that it is accelerating, which is faster than planned. The S-curveabove the planning S-curve indicates a slowdown in project work, while the S-curve below the planning S-curve, indicates a slowdown in project work. In this study, it was found that there was a greater slowdown in project work compared to the acceleration of project work. With this study, the results of the comparison of the delay before the addendum are 1.041 and the comparison of the delay after the addendum is 1.171.

Item Type: Thesis (Masters)
Additional Information: Cornelia Agda Santoso NIM : 22073000001
Uncontrolled Keywords: S-Curve, Sequential Delays, Project Management, Bromo Tengger Semeru National Park
Subjects: N Fine Arts > NA Architecture
Divisions: Program Pascasarjana > S2 Magister Arsitektur
Depositing User: Gendhis Dwi Aprilia
Date Deposited: 28 Oct 2026 02:48
Last Modified: 28 Oct 2026 02:48
URI: https://eprints.unmer.ac.id/id/eprint/5671